• SP: South Pars
• SRU :Sculpture Recovery Unit
• SPIFON :South Pars Integrated Fiber Optic Network
• TBE :Technical Bid Evaluation
• TIJD: Toyo , Idro , Jgc , Daelim ( consortium)
• U/G :Underground
• UPS: Uninterrupted Power Supply
• WBS: Work Breakdown Structure
• WP: Work Package
• WHP :Well Head Platform
• NPV: Net Present Value
• OPEX :Operational Expenditure
• PCS: Process Control System
• PDCS :Power Distribution Control System
• PFO :Process Flow Diagram
• PID :Piping & Instrument Diagram
• PPM :Parts Per Million
• PTR :Project Technical Review
• PDH :Plesiochronous Digital Hierarchy
• PO :Purchase Order
• PMS :Progress Measurement System
• PMT :Project Management Team
• PBG: Performance Bank Guarantee
• PWHT: Post Weld Heat Treatment
• QA: Quality Assurance
• QC: Quality Control
• RSH: Mercaptan
• SBM :Single Buoy Mooring
• ITR: Instrument Technical Room
• JMC :Joint Management Committee
• JV :Joint Venture
• KOM: Kick‐Off Meeting
• KO :Drum Knockout Drum
• LAN :Local Area Network
• LLI :Long Lead Item
• LNG: Liquefied Natural Gas
• LPG: Liquefied Pressured Gas
• LOI :Letter Of Intent
• LTI :Lost Time Incident
• MEG :Mono Ethylene Glycol/Methyl Ethyl Glycol
• MMSCFD: Million Standard Cubic Foot / Day
• MOV :Motor Operated Valve
• MTO :Material Take‐Off
• MDP: Master Development Plan
• NDT :Non Destructive Testing
• NGL :Natural Gas Liquid
• FEED :Front End Engineering & Design
• FID : Final Investment Decision
• FO : Fiber Optic / Fail Open
• FWKO : Free Water Knockout
• FPSO :Floating Production and Storage and Offloading
• GTG :Gas Turbine Generator
• HAZID :Hazards Identification
• HAZOP :Hazards & Operability
• HIPPS :High Integrity Pressure Protective System
• HSE :Health , Safety , Environment
• HV: High Voltage
• HVAC : Heating , Ventilation and Air Conditioning
• IFA: Issued For Approval
• IFC :Issued For Comment
• IFD: Issued For Design
• ICSS: Integrated Control & Supervisory System
• ITB: Invitation To Bid
.A/G :Above‐Ground
• AFC :Approve For Construction
• AP :Advance Payment
• BGCS: Booster Gas Compressor Station
• CAPEX: Capital Expenditure
• CFT :Call For Tender
• CBS: Cost Breakdown Structure
• CIS :Change In Scope
• COI :Change Order Instruction
• COR: Change Order Request
• DCS :Distributed Control System
• DSO :Disulfide Oil
• EIA: Environment Impact Assessment
• EPC : Engineering, Procurement, Constriction
• EPSCC :Engineering, Procurement, Supply, Construction Commissioning
• ESO :Emergency Shutdown
• FGS :Fire & Gas System
برچسبها: مخفف های کاربردی مهندسی ساختار شکست کار چیست (WBS)...
ما را در سایت ساختار شکست کار چیست (WBS) دنبال می کنید
برچسب : نویسنده : abraheh بازدید : 301 تاريخ : چهارشنبه 24 خرداد 1396 ساعت: 11:00